Work Profile Report [5W844]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 4601/।।।(2)/21-47(एम0एल0ए0)/2017टी0सी0-।, दिनांक 29.09.2021
TS Amount (lakhs) : 86.93 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
86.93
Resanction Cost :
86.93
Tentative Cost :
86.93
Exp. Upto Last Fy :
80.50
For CFY 2024-2025
Remaining :
6.43
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
80.50
Work completed
Sanction on : 3 years 1 month ago
29 Sep 2021
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
80 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date : 2 years 4 months ago
30 Jun 2022
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष -- as on 05-Jul-2022
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2
Bridges on The Basis of AI: 36.00 m span steel bridge 30 m span motor bridge 6 m span Motor Brisge at Dangoli syali chatiya
© PWD Uttarakhand