Work Profile Report [5W900]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-।/111079/2023, ई फाईल संख्या-35078, दिनांक 29.03.2023
TS Amount (lakhs) : 241.35 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
252.12
Resanction Cost :
252.12
Tentative Cost :
244.12
Saving
8.00
Exp. Upto Last Fy :
103.08
For CFY 2024-2025
Remaining :
149.04
Demand :
111.00
Allotment :
80.00
Exp in CFY :
45.83
Total Up to Date Exp :
148.91
Construction Started
Sanction on : 1 year 7 months ago
29 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
33 %
Up to Date :
65 %
Tentative Completion date on : 1 month 1 week from now
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
400मी0 लम्बाई में लगातार भूधसाव होने के कारण जी0-1,जी0-2 एवं जी0-3 का कार्य नहीं किया जा सका है। -- as on 14-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: