Work Profile Report [5W902]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-।/111079/2023, ई फाईल संख्या-35078, दिनांक 29.03.2023
TS Amount (lakhs) : 124.36 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
124.36
Resanction Cost :
124.36
Tentative Cost :
124.36
Exp. Upto Last Fy :
74.23
For CFY 2024-2025
Remaining :
50.13
Demand :
44.02
Allotment :
40.00
Exp in CFY :
44.38
Total Up to Date Exp :
118.61
In Maintenance After Completion
Sanction on : 1 year 7 months ago
29 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
55 %
Up to Date :
100 %
Tentative Completion date on : 4 months 3 days ago
20 Jul 2024
Actual Completion Date : 5 months 2 weeks ago
05 Jun 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 13-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: