Work Profile Report [5W903]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-।/111076/2023, ई फाईल संख्या-48414, दिनांक 29.03.2023
TS Amount (lakhs) : 239.37 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
239.37
Resanction Cost :
239.37
Tentative Cost :
239.37
Exp. Upto Last Fy :
171.05
For CFY 2024-2025
Remaining :
68.32
Demand :
64.91
Allotment :
65.00
Exp in CFY :
56.86
Total Up to Date Exp :
227.90
Construction Started
Sanction on : 1 year 8 months ago
29 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
70 %
Up to Date :
90 %
Tentative Completion date on : 2 months 2 weeks ago
10 Oct 2024
Actual Completion Date : 3 months 2 weeks ago
11 Sep 2024
Physical Linear Components
Remark
पी0सी0 कार्य पूर्ण। -- as on 22-Jun-2024
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Kajuli-kotfilwari Bridge