Work Profile Report [5W904]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-।/111076/2023, ई फाईल संख्या-48414, दिनांक 29.03.2023
TS Amount (lakhs) : 203.82 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
203.82
Resanction Cost :
203.82
Tentative Cost :
188.82
Saving
15.00
Exp. Upto Last Fy :
179.51
For CFY 2025-2026
Remaining :
24.31
Demand :
19.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
179.51
Construction Started
Sanction on : 2 years 1 week ago
29 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
40 %
Up to Date :
92 %
Tentative Completion date on : 2 months 1 week ago
31 Jan 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 15 has been recorded as expected cost of work reduced from 203.82 to 188.82 . -- as on 18-Dec-2024
Assets :