Work Profile Report [5W929]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, देहरादून के पत्रांक 895/07याता0-पी0एम0जी0एस0वाई0-नि0।।।, दिनांक 18.05.2023
TS Amount (lakhs) : 153.03 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
153.03
Resanction Cost :
153.03
Tentative Cost :
153.03
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
153.03
Demand :
85.00
Allotment :
32.00
Exp in CFY :
64.59
Total Up to Date Exp :
64.59
Construction Started
Sanction on : 1 year 6 months ago
18 May 2023
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
70 %
Tentative Completion date on : 2 months 3 weeks ago
31 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
7 किमी0 पी0सी0 कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 21-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: