Work Profile Report [5W936]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-।/135768/2023, ई फाईल संख्या-35078, दिनांक 07.07.2023
TS Amount (lakhs) : 86.19 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
86.19
Resanction Cost :
86.19
Tentative Cost :
86.19
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
86.09
Demand :
62.37
Allotment :
40.00
Exp in CFY :
45.31
Total Up to Date Exp :
45.41
Construction Started
Sanction on : 1 year 4 months ago
07 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
60 %
Tentative Completion date on : 2 months 1 week ago
13 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दीवार एवं स्कपर कार्य प्रगति पर। -- as on 06-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: