Work Profile Report [60W10]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : MOrt&H No 28014/01/2014/UR/CRF/NH-2 Dated 31.302016 Uk Govt. G.O No. 432/III(3)/2016-01(CRF)/2012 dated 30.7.16
TS Amount (lakhs) : 2710.94 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2819.00
Resanction Cost :
2819.00
Tentative Cost :
2819.00
Exp. Upto Last Fy :
2,472.84
For CFY 2024-2025
Remaining :
346.16
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2,472.84
Work completed
Sanction on : 8 years 8 months ago
31 Mar 2016
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 4 months ago
31 Jul 2023
Actual Completion Date : 1 year 4 months ago
31 Jul 2023
Physical Linear Components
Remark
WorkCompleted. -- as on 14-Dec-2023
Assets :