Administrative Approval Detail : RO/UK/Annual Plan/2022-23/Dehradun/09
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
499.38
Resanction Cost :
499.38
Tentative Cost :
499.38
Exp. Upto Last Fy :
273.38
For CFY 2025-2026
Remaining :
226.00
Demand :
0.00
Allotment :
273.38
Exp in CFY :
0.00
Total Up to Date Exp :
273.38
Construction Started
Sanction on : 2 years 1 month ago
02 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
55 %
Up to Date :
90 %
Tentative Completion date on : 6 months 4 weeks ago
07 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work in progress. -- as on 10-Nov-2023