Work Profile Report [60W5]
Fin Plan
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : RO/UK/12014/20/Annual Plan/2021-22 Dated 24.02.2020 Job No. 72(07)-UR-2021-22-564
TS Amount (lakhs) : 1054.32 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1054.32
Resanction Cost :
1054.32
Tentative Cost :
1054.32
Exp. Upto Last Fy :
555.43
For CFY 2024-2025
Remaining :
498.89
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
555.43
Construction Started
Sanction on : 4 years 9 months ago
24 Feb 2020
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 1 month ago
04 Oct 2021
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work Completed. Liabilities Due. -- as on 30-Nov-2021
Assets :
© PWD Uttarakhand