Work Profile Report [60W7]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : RO/UK/Annual Plan/2021-22/Dehradun-02 Date 24.12.2020 Job No. NH-334A(307)-UR-2021-22-572
TS Amount (lakhs) : 850 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
850.00
Resanction Cost :
850.21
Tentative Cost :
850.21
Exp. Upto Last Fy :
351.98
For CFY 2025-2026
Remaining :
498.23
Demand :
0.00
Allotment :
315.09
Exp in CFY :
0.00
Total Up to Date Exp :
351.98
Construction Started
Sanction on : 4 years 3 months ago
24 Dec 2020
Physical Progress:
At start of FY 2025-2026 :
30 %
Up to Date :
94 %
Tentative Completion date on : 6 months 6 days ago
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work in progress. -- as on 20-May-2023
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2
Bridges on The Basis of AI: Hadvaha Nala Bridge
© PWD Uttarakhand