Work Profile Report [61W1]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : कार्य की प्रशासकीय स्वीकृति भारत सरकार के पत्र सं0 एन0एन0 28014/01/2014/यू0आर0/सी0आर0एफ0/एन0एच0-2 (जोन-1) दिनांक 20 फरवरी 2019 द्वारा प्राप्त हुई है।
TS Amount (lakhs) : 1003.77 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1093.27
Resanction Cost :
1093.27
Tentative Cost :
1093.27
Exp. Upto Last Fy :
508.11
For CFY 2024-2025
Remaining :
585.16
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
508.11
Work completed
Sanction on : 5 years 9 months ago
20 Feb 2019
Physical Progress:
At start of FY 2024-2025 :
65 %
Up to Date :
100 %
Tentative Completion date on : 2 years 7 months ago
20 Apr 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Bridge Fabrication and ground erection completed. Both abutment work completed up to 55% and in progress. -- as on 17-Aug-2021
Assets :