Work Profile Report [62W2]

Closed Work एन0एच0 94(134) के किमी 147.00 से 157.00 में रोड सुदृढीकरण का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

Administrative Approval Detail : RO/UK/12014/105/Annual plan/2019-20 Job.no-NH-94(134)-UR-2019-20-551

TS Amount (lakhs) : 707.66 Lacs

Budget Financial Head : Not Available

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

707.66

Resanction Cost :

707.66

Tentative Cost :

707.66

Exp. Upto Last Fy :

437.00

For CFY 2024-2025

Remaining :

270.66

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

437.00

Construction Started

Sanction on : 4 years 7 months ago

13 Jan 2020

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

100 %

Tentative Completion date on : 2 years 6 months ago

25 Jan 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
10
10
10
-

Remark

view all

Physical progress-100%
financial progress-87%
DBM Completed- 10.00 km
BC Completed-10.00 km
-- as on 18-Feb-2022

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1 Road 2

Bridges on The Basis of AI: Junga Bridge

© PWD Uttarakhand