Work Profile Report [62W5]
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : एन0एच0 12014/105/2016/यू0आर0/चारधाम/एन0एच0-2job no. NH-94-UR-2016-17-496
TS Amount (lakhs) : 23780.53 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
23780.00
Resanction Cost :
23780.00
Tentative Cost :
23780.00
Exp. Upto Last Fy :
15,207.72
For CFY 2024-2025
Remaining :
8,572.28
Demand :
1,000.00
Allotment :
256.28
Exp in CFY :
256.28
Total Up to Date Exp :
15,464.00
Construction Started
Sanction on : 7 years 7 months ago
28 Mar 2017
Physical Progress:
At start of FY 2024-2025 :
96 %
Up to Date :
97 %
Tentative Completion date on : 6 months 3 weeks ago
30 Apr 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
physical progress 97.42 %
financial progress-95.20 %
-- as on 06-Jun-2024
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2 Road 3
Bridges on The Basis of AI: Margaon Bridge Junga Bridge local nala
© PWD Uttarakhand