Work Profile Report [63W2]
Fin Plan
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : फा० संख्या - एन० एच० 12014 /24/2017/यू० आर०/एन०एच० -02 दिनांक 23 अगस्त 2017
TS Amount (lakhs) : 1530.16 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1530.16
Resanction Cost :
1530.16
Tentative Cost :
1530.16
Exp. Upto Last Fy :
963.87
For CFY 2024-2025
Remaining :
566.29
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
963.87
Work completed
Sanction on : 7 years 3 months ago
23 Aug 2017
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 3 years 11 months ago
25 Dec 2020
Actual Completion Date : 3 years 11 months ago
25 Dec 2020
Physical Linear Components
Remark
Km 174 -Bridge work completed, km 181- Bridge work completed, km 157- Bridge work completed and Work will be Fore close due Wild life NOC not Provided by Forest department. -- as on 08-Jan-2023
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: NEAR BAIRGAON SULYA BRIDGE JOGIYANA SUSPENSION BRIDGE