Work Profile Report [63W3]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : फा० सं० एन० एच०-12014 /33 /2017 /यू० आर०/जोन -1 दिनांक 27 मार्च 2018
TS Amount (lakhs) : 1640.18 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1640.18
Resanction Cost :
1640.18
Tentative Cost :
1640.18
Exp. Upto Last Fy :
523.23
For CFY 2025-2026
Remaining :
1,116.95
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
523.23
Construction Started
Sanction on : 7 years 1 week ago
27 Mar 2018
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
48 %
Tentative Completion date on : 2 years 1 month ago
28 Feb 2023
Actual Completion Date : 1 year 11 months ago
30 Apr 2023
Physical Linear Components
Remark
02 Nos Bridges in km. 158 & 156 are completed. 3 Nos bridge at km 152, 163, 165 not started due to forest land. In forest proposal Stage-I approval accorded by regional office on 28.12.22 Work fore closer proposal sent on 19.01.2023. -- as on 19-Apr-2023
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Majhgaon Bridge Majhgaon Bridge