Work Profile Report [63W5]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : फा० सं० एन०एच०-12014 /34 /2017/यू०आर०/जोन -1 दिनांक 27 मार्च 2018
TS Amount (lakhs) : 1351.64 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1351.64
Resanction Cost :
1351.64
Tentative Cost :
1351.64
Exp. Upto Last Fy :
795.15
For CFY 2024-2025
Remaining :
556.49
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
795.15
Construction Started
Sanction on : 6 years 10 months ago
27 Mar 2018
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
74 %
Tentative Completion date on : 2 years 1 day ago
31 Jan 2023
Actual Completion Date : 1 year 6 months ago
04 Jul 2023
Physical Linear Components
Remark
03 Nos bridges in Km. 149, km 138 & Km 121 are completed, in km. 141 contractor inform to division in writing that he is not able to start work due to delay in forest clearance & non availability of dumping zone. Work fore closer proposal sent on 19.01.2023. -- as on 19-Apr-2023
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: KARODA BRIDGE MAITHGHAT BRIDGE Jiwai Kakroda Bridge