Work Profile Report [67W711]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 700/30 खनन/न्यास/2023-24 दि0 02.05.2023
TS Amount (lakhs) : 194.29 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
194.29
Resanction Cost :
209.29
Tentative Cost :
194.29
Saving
15.00
Exp. Upto Last Fy :
115.54
For CFY 2024-2025
Remaining :
93.75
Demand :
78.75
Allotment :
93.75
Exp in CFY :
73.90
Total Up to Date Exp :
189.43
Work completed
Sanction on : 1 year 6 months ago
05 May 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 8 months 1 week ago
15 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्य शेष। -- as on 12-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand