Work Profile Report [67W755]

स्यालखाल-पंवाई मोटर मार्ग का सुधारीकरण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : लोक निर्माण अनुभाग-2 ई0 पत्रावली सं0 48456 दि0 23.02.2024

TS Amount (lakhs) : 150.41 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

150.41

Resanction Cost :

150.41

Tentative Cost :

150.41

Exp. Upto Last Fy :

0.00

For CFY 2024-2025

Remaining :

150.41

Demand :

100.00

Allotment :

60.09

Exp in CFY :

37.47

Total Up to Date Exp :

37.47

Work completed

Sanction on : 10 months 2 days ago

23 Feb 2024

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

100 %

Tentative Completion date on : 3 months 1 week ago

13 Sep 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
7.95
7.95
0.000
7.95
7.950
0.000
Jobs
1
1
0
1
0
0

Remark

view all

कार्य पूर्ण। दायित्य शेष। -- as on 22-Oct-2024

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI:

© PWD Uttarakhand