Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 12 | 12 | 0 |
68W31 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 3274 ए0/।।।(2)/17-39 (एम0एल0ए0)/2017
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
60.60
Resanction Cost :
60.60
Tentative Cost :
60.60
Exp. Upto Last Fy : 2.14
For CFY 2024-2025
Remaining : 58.46
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.14
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 5 %
Sanction on :
6 years 6 months ago
27 Dec 2017
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 03: DM
Bottelneck: CA Land
इस कार्यालय की ई-पत्रावली सं0 1/91485/2024 दिनांक 27.06.2024 के द्वारा 3.350 हे के बदले दोगुनी भमि 6.700 हे0 उपलब्ध कराने हेतु जिलाधिकारी महोदय पौड़ी को लिखा गया है। भूमि उपलब्ध होने के उपरान्त ही वनभूमि प्रस्ताव गठित कर पाना सम्भव हो पायेगा। -- as on 27-Jun-2024
Physical Peramenters