Work Profile Report [69W17]

Closed Work डोभ श्रीकोट जामणाखाल हुलाकीखाल मो. मार्ग का विस्तार
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 572/(1)/111 - 2/ 05 दिनांक 28.3.06

TS Amount (lakhs) : 99.05 Lacs

Budget Financial Head : Not Available

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

166.50

Resanction Cost :

166.50

Tentative Cost :

85.96

Saving

80.54

Exp. Upto Last Fy :

85.96

For CFY 2025-2026

Remaining :

80.54

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

85.96

Work deferred

Sanction on : 19 years 4 weeks ago

28 Mar 2006

Physical Progress:

At start of FY 2025-2026 :

60 %

Up to Date :

60 %

Tentative Completion date on : 3 weeks 5 days ago

31 Mar 2025

Actual Completion Date : 3 weeks 5 days ago

31 Mar 2025

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
13
8.5
8.5
-

Remark

view all

Overall Saving 80.54 has been recorded as expected cost of work reduced from 166.5 to 85.96 . -- as on 08-Apr-2025

Rating : 60

Forest Case Pending At : 01: Withdraw

Hindrance / Bottleneck : Alignment Dispute

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: