Work Profile Report [69W17]

डोभ श्रीकोट जामणाखाल हुलाकीखाल मो. मार्ग का विस्तार
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 572/(1)/111 - 2/ 05 दिनांक 28.3.06

TS Amount (lakhs) : 99.05 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

166.50

Resanction Cost :

166.50

Tentative Cost :

83.73

Saving

82.77

Exp. Upto Last Fy :

83.73

For CFY 2024-2025

Remaining :

82.77

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

83.73

Work deferred

Sanction on : 18 years 5 months ago

28 Mar 2006

Physical Progress:

At start of FY 2024-2025 :

60 %

Up to Date :

60 %

Tentative Completion date on : 6 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
13
8.5
8.5
-

Remark

view all

Overall Saving 82.77 has been recorded as expected cost of work reduced from 166.5 to 83.73 . -- as on 02-Aug-2024

Rating : 64

Forest Case Pending At : 01: Withdraw

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI:

© PWD Uttarakhand