Administrative Approval Detail : शासनादेश सं0 2490/111(2)/08-61(प्रा0आ0) /2007 दिनांक 25 जुलाई, 2008
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
725.41
Resanction Cost :
725.41
Tentative Cost :
66.72
Saving
658.69
Exp. Upto Last Fy :
66.72
For CFY 2025-2026
Remaining :
658.69
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
66.72
Alignment Approved
Sanction on : 17 years 5 months ago
25 Jul 2008
Physical Progress:
At start of FY 2025-2026 :
2 %
Up to Date :
2 %
Tentative Completion date on : 2 years 11 months from now
31 Dec 2028
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वनभूमि प्रस्ताव आनलाइन किया गया है। -- as on 26-Dec-2025