Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 0.000 | 7 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
6W116 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 2490/111(2)/08-61(प्रा0आ0) /2007 दिनांक 25 जुलाई, 2008
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
725.41
Resanction Cost :
725.41
Tentative Cost :
725.41
Exp. Upto Last Fy : 66.72
For CFY 2024-2025
Remaining : 658.69
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 66.72
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 2 %
Up to Date : 2 %
Sanction on :
15 years 11 months ago
25 Jul 2008
Tentative Completion date:
2 years 5 months from now
31 Dec 2026
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 03: DM
Bottelneck: no issue
वनभूमि प्रस्ताव आपत्ति में प्राप्त। क्षतिपूरक वृक्षारोपण स्तर की वर्तमान वैधानिक स्थिति से अवगत कराए जाने हेतु आपत्ति दर्ज की गई है। क्षतिपूरक वृक्षारोपण हेतु दुगनी भूमि का संयुक्त निरीक्षण राजस्व विभाग एवं वन विभाग के साथ दिनांक 05.03.2024 को किया गया। आख्या अपेक्षित है। -- as on 28-Apr-2024
Physical Peramenters