Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 0.000 | 7 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
6W116 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 2490/111(2)/08-61(प्रा0आ0) /2007 दिनांक 25 जुलाई, 2008
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 725.41 Lacs
Resanction Cost : 725.41 Lacs
Exp. Upto Last Fy : 66.72 Lacs
For CFY 2024-2025
Remaining : 658.69 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 66.72 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 2 %
Up to Date : 2 %
Sanction on :
15 years 9 months ago
25 Jul 2008
Tentative Completion date:
2 years 7 months from now
31 Dec 2026
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
वनभूमि प्रस्ताव आपत्ति में प्राप्त। क्षतिपूरक वृक्षारोपण स्तर की वर्तमान वैधानिक स्थिति से अवगत कराए जाने हेतु आपत्ति दर्ज की गई है। क्षतिपूरक वृक्षारोपण हेतु दुगनी भूमि का संयुक्त निरीक्षण राजस्व विभाग एवं वन विभाग के साथ दिनांक 05.03.2024 को किया गया। आख्या अपेक्षित है। -- as on 28-Apr-2024
Physical Peramenters