Work Profile Report [6W123]

बागेश्वर में कन्यालीकोट जगन्थाना मोटर मार्ग के किमी0 4 से पैसारी तक मार्ग निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

Administrative Approval Detail : शासनादेश सं0 2490/111(2)/08-61(प्रा0आ0) /2007 दिनांक 25 जुलाई, 2008

TS Amount (lakhs) : 287.7 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

287.70

Resanction Cost :

287.70

Tentative Cost :

287.70

Exp. Upto Last Fy :

139.64

For CFY 2024-2025

Remaining :

148.06

Demand :

85.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

139.64

in Tendering Stage

Sanction on : 16 years 3 weeks ago

25 Jul 2008

Physical Progress:

At start of FY 2024-2025 :

55 %

Up to Date :

55 %

Tentative Completion date on : 1 year 4 months from now

31 Dec 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
6
6
3.000
3
0.000
0.000
Bridge
2
2 (36m)
0 (0.000m)
2 (36m)
1 (18.000m)
0 (0.000m)

Remark

view all

3 किमी कार्य पूर्ण।
किमी0 1 में 18 मी0 सेतु निर्माण हेतु अनुबंध गठन की कार्यवाही की जा रही है। सेतु का कार्य पूर्ण होने के उपरान्त अवशेष 3 किमी0, 1 सेतु हेतु पुनरीक्षित आगणन गठित कर प्रेषित किया जाएगा।
-- as on 06-Apr-2024

Rating : 65

Forest Case Pending At : 21: Final

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI:

© PWD Uttarakhand