Work Profile Report [6W701]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ‘शा.सं. 5663/।।।(2)/21- 46(एम0एल0ए0)/2017 टी0सी0 दिनांक 17.11.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
27.42
Resanction Cost :
27.42
Tentative Cost :
27.42
Exp. Upto Last Fy :
0.03
For CFY 2024-2025
Remaining :
27.39
Demand :
2.72
Allotment :
1.52
Exp in CFY :
1.52
Total Up to Date Exp :
1.55
Alignment Approved
Sanction on : 3 years 6 days ago
17 Nov 2021
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
26 %
Tentative Completion date on : 11 months 1 week from now
31 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पेडो की गणना हेतु पिलरो का निर्माण कार्य किया जा रहा है। -- as on 10-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand