Work Profile Report [6W710]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : dsto letter no 525/जि0यो0(1)/2021-22, dated 05-07-2021
TS Amount (lakhs) : 12 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
12.00
Resanction Cost :
12.00
Tentative Cost :
12.00
Exp. Upto Last Fy :
8.55
For CFY 2024-2025
Remaining :
3.45
Demand :
3.40
Allotment :
0.00
Exp in CFY :
1.83
Total Up to Date Exp :
10.38
Work completed
Sanction on : 3 years 4 months ago
05 Jul 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 6 months ago
24 Apr 2023
Actual Completion Date : 1 year 6 months ago
24 Apr 2023
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 24-Apr-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand