Work Profile Report [6W795]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : कार्यालय जिला जिलाधिकारी बागे0 के पत्र सं0 698/तीस-86/खनन-जि0ख0फा0न्यास(2017-18)/2022-23 दिनांक 04.05.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
32.81
Resanction Cost :
32.81
Tentative Cost :
32.81
Exp. Upto Last Fy :
14.29
For CFY 2024-2025
Remaining :
18.52
Demand :
15.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
14.29
Construction Started
Sanction on : 1 year 3 months ago
04 May 2023
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
80 %
Tentative Completion date on : 2 months 2 weeks from now
31 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 16-Oct-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: