Work Profile Report [6W797]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई फाइत संख्या 31978 दिनांक 04.05.2023
TS Amount (lakhs) : 98.88 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
98.88
Resanction Cost :
99.88
Tentative Cost :
91.00
Saving
8.88
Exp. Upto Last Fy :
36.84
For CFY 2024-2025
Remaining :
63.04
Demand :
58.49
Allotment :
54.12
Exp in CFY :
54.12
Total Up to Date Exp :
90.96
Work completed
Sanction on : 1 year 7 months ago
04 May 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 8 months 3 weeks ago
31 Mar 2024
Actual Completion Date : 8 months 3 weeks ago
29 Mar 2024
Physical Linear Components
Remark
Overall Saving 8.88 has been recorded as expected cost of work reduced from 99.88 to 91 . -- as on 18-Dec-2024
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2 Road 3 Road 4
Bridges on The Basis of AI: 60 Meter Span steel girder Motor bridge 24 Mtr Tiladi Pedestrain Bridge