Work Profile Report [6W801]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई0 फाईल सं0 50154 दिनांक 17.05.2023
TS Amount (lakhs) : 214.58 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
214.58
Resanction Cost :
214.58
Tentative Cost :
190.03
Saving
24.55
Exp. Upto Last Fy :
188.10
For CFY 2025-2026
Remaining :
26.48
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
188.10
In Maintenance After Completion
Sanction on : 1 year 10 months ago
17 May 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 9 months 2 weeks ago
25 Jun 2024
Actual Completion Date : 9 months 2 weeks ago
25 Jun 2024
Physical Linear Components
Remark
Overall Saving 24.55 has been recorded as expected cost of work reduced from 214.58 to 190.03 . -- as on 05-Apr-2025