Work Profile Report [6W803]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : ई फाइत संख्या 31978 दिनांक 14.07.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
187.54
Resanction Cost :
187.54
Tentative Cost :
143.00
Saving
44.54
Exp. Upto Last Fy :
48.08
For CFY 2024-2025
Remaining :
139.46
Demand :
83.47
Allotment :
63.47
Exp in CFY :
63.47
Total Up to Date Exp :
111.55
Construction Started
Sanction on : 1 year 1 month ago
14 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
70 %
Tentative Completion date on : 1 month 4 weeks from now
15 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 44.54 has been recorded as expected cost of work reduced from 187.54 to 143 . -- as on 10-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: