Work Profile Report [6W808]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी बागे0 के पत्र सं0 716/जि0यो0(1)/2023-24 दिनांक 06.07.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
20.00
Resanction Cost :
20.00
Tentative Cost :
20.00
Exp. Upto Last Fy :
16.89
For CFY 2024-2025
Remaining :
3.11
Demand :
2.00
Allotment :
0.00
Exp in CFY :
3.01
Total Up to Date Exp :
19.90
Construction Started
Sanction on : 1 year 4 months ago
06 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
80 %
Tentative Completion date on : 1 month 1 week from now
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 25-Oct-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: