Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 0 | 0 | 0 | 0 |
6W855 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0-4088/।।।(2)/2023-(पा0आ0)/2023 दिनांक 01.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
60.31
Resanction Cost :
60.31
Tentative Cost :
60.31
Exp. Upto Last Fy : 35.52
For CFY 2024-2025
Remaining : 24.79
Demand : 24.00
Allotment : 0.75
Exp in CFY : 0.75
Total Up to Date Exp : 36.27
Construction Started
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 90 %
Sanction on :
8 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
1 month 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
क्रश बैरियर का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 13-Jul-2024
Physical Peramenters