Work Profile Report [6W857]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : आवास अनुभाग-2 उत्तराखण्ड शासन के ई पत्रावली सं0 33412 दिनांक 19.10.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
55.19
Resanction Cost :
55.19
Tentative Cost :
55.19
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
55.19
Demand :
40.00
Allotment :
6.11
Exp in CFY :
6.11
Total Up to Date Exp :
6.11
Construction Started
Sanction on : 9 months 4 weeks ago
19 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
30 %
Tentative Completion date on : 1 year 2 weeks from now
31 Aug 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दीवार निर्माण कार्य प्रगति पर है। -- as on 13-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: