Work Profile Report [70W157]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शा0सं0 1755/155(2)/18-40 (एम0एल0ए0)/2017 दि0 03.05.2018
TS Amount (lakhs) : 155.03 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
155.19
Resanction Cost :
155.19
Tentative Cost :
155.19
Exp. Upto Last Fy :
155.18
For CFY 2024-2025
Remaining :
0.01
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
155.18
In Maintenance After Completion
Sanction on : 6 years 10 months ago
03 May 2018
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 11 months ago
31 Mar 2023
Actual Completion Date : 2 years 1 week ago
20 Feb 2023
Physical Linear Components
Remark
कार्य पूर्ण। उक्त कार्य की पी0सी0आर0 दिनांक 24-12-2024 को अधीक्षण अभियन्ता कार्यालय पौड़ी को प्रेषित की जा चुकी है। -- as on 31-Jan-2025
Assets :
© PWD Uttarakhand