Work Profile Report [70W237]

Closed Work जनपद पौड़ी गढ़वाल के विकासखण्ड रिखणीखाल में सिन्धी -बामसू-अन्दा्रेली मोटर मार्ग निर्माण (द्वितीय चरण)।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 697ए/।।।(2)/19-40(एम0एल0ए0)/ 2017 दि0 18.02.2019

TS Amount (lakhs) : 156 Lacs

Budget Financial Head : Not Available

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

156.14

Resanction Cost :

156.14

Tentative Cost :

156.14

Exp. Upto Last Fy :

0.00

For CFY 2024-2025

Remaining :

156.14

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Construction Started

Sanction on : 5 years 9 months ago

18 Feb 2019

Physical Progress:

At start of FY 2024-2025 :

60 %

Up to Date :

60 %

Tentative Completion date on : 1 year 7 months ago

31 Mar 2023

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3
3
3
-

Remark

view all

नाबार्ड-27 में वित्त पोषित। पहाड़ कटान पूर्ण हो गया है। पार्ट-2 का कार्य प्रगति पर है। -- as on 20-Jul-2022

Rating : 88

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI:

© PWD Uttarakhand