Work Profile Report [70W277]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0स0 4015(1)/।।।(2)/21-36 (एम0एल0ए0) /2017 टी0सी0-01 दिनांक 17.09.2021
TS Amount (lakhs) : 124.31 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
124.31
Resanction Cost :
124.31
Tentative Cost :
124.31
Exp. Upto Last Fy :
119.70
For CFY 2025-2026
Remaining :
4.61
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
119.70
Work completed
Sanction on : 3 years 6 months ago
17 Sep 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 1 week ago
31 Mar 2023
Actual Completion Date : 2 years 3 months ago
31 Dec 2022
Physical Linear Components
Remark
पहाड़ कटान का कार्य पूर्ण। -- as on 08-Nov-2023
Assets :
© PWD Uttarakhand