Administrative Approval Detail : ई0 फाईल न0 36089 दि0 31-03-2023
TS Amount (lakhs) : 343.61 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
343.61
Resanction Cost :
343.61
Tentative Cost :
343.61
Exp. Upto Last Fy :
336.90
For CFY 2025-2026
Remaining :
6.71
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
336.90
In Maintenance After Completion
Sanction on : 2 years 2 weeks ago
31 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 5 months 1 week ago
02 Nov 2024
Actual Completion Date : 9 months 3 weeks ago
22 Jun 2024
Physical Linear Components
Remark
कार्य पूर्ण। पी0सी0आर0 प्रेषित । -- as on 13-Nov-2024
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: JADAUKHAND-MAJEDABEND BAILEY BRIDGE-1