Work Profile Report [70W416]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 50713, दि0 15.03.2023
TS Amount (lakhs) : 286.77 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
286.77
Resanction Cost :
286.77
Tentative Cost :
286.77
Exp. Upto Last Fy :
196.73
For CFY 2025-2026
Remaining :
90.04
Demand :
0.00
Allotment :
225.00
Exp in CFY :
0.00
Total Up to Date Exp :
196.73
Construction Started
Sanction on : 2 years 3 weeks ago
15 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
15 %
Up to Date :
65 %
Tentative Completion date on : 3 months 2 days ago
04 Jan 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
W.B.M. का कार्य पूर्ण। मोैसम अनूकूल होने पर पी0सी0 का कार्य किया जायेगा। -- as on 02-Sep-2024