Work Profile Report [70W457]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली संख्या-48456, दिनांक 10.08.2023
TS Amount (lakhs) : 201.41 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
201.41
Resanction Cost :
201.41
Tentative Cost :
201.41
Exp. Upto Last Fy :
199.84
For CFY 2025-2026
Remaining :
1.57
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
199.84
Work completed
Sanction on : 1 year 8 months ago
10 Aug 2023
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
100 %
Tentative Completion date on : 8 months 3 weeks ago
19 Jul 2024
Actual Completion Date : 9 months 3 weeks ago
18 Jun 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 25-Feb-2025
Assets :