Work Profile Report [70W457]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली संख्या-48456, दिनांक 10.08.2023
TS Amount (lakhs) : 201.41 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
201.41
Resanction Cost :
201.41
Tentative Cost :
201.41
Exp. Upto Last Fy :
49.73
For CFY 2024-2025
Remaining :
151.68
Demand :
151.68
Allotment :
141.00
Exp in CFY :
140.63
Total Up to Date Exp :
190.35
Work completed
Sanction on : 1 year 3 months ago
10 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
100 %
Tentative Completion date on : 4 months 4 days ago
19 Jul 2024
Actual Completion Date : 5 months 5 days ago
18 Jun 2024
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का अन्तिमीकरण किया जा रहा है। -- as on 25-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: