Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 3.000 | 3.000 |
70W509 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 48456, दि0 30.01.2024
TS Amount (lakhs) : 58.43 Lacs
Financial Detail
Sanction Cost : 58.43 Lacs
Resanction Cost : 58.43 Lacs
Exp. Upto Last Fy : 0.04 Lacs
For CFY 2024-2025
Remaining : 58.39 Lacs
Demand : 58.39 Lacs
Allotment : 25.00 Lacs
Exp in CFY : 40.47 Lacs
Total Up to Date Exp : 40.51 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 100 %
Sanction on :
4 months 3 days ago
30 Jan 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 का कार्य पूर्ण। -- as on 22-May-2024