Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 26.8 | 26.8 | 0.000 | 26.8 | 26.800 | 11.000 |
70W527 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन के पत्रांक सं0 294/।।।(3)/2024-01(सी0आर0आई0एफ0)2024, दि0 12.03.2024 एवं पत्रांक 256/।।।(3)/2024-01(सी0आर0आई0एफ0)2022, दि0 09.02.2024, एवं 322/।।।(3)/2024-14(सी0आर0आई0एफ0)2024, दि0 06-03-2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1383.21
Resanction Cost :
1383.21
Tentative Cost :
1383.21
Exp. Upto Last Fy : 8.26
For CFY 2024-2025
Remaining : 1,374.95
Demand : 1,374.95
Allotment : 300.00
Exp in CFY : 194.25
Total Up to Date Exp : 202.50
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 45 %
Sanction on :
4 months 5 days ago
12 Mar 2024
Tentative Completion date:
7 months 3 weeks from now
14 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
बी0एम0 एवं बी0सी0 का कार्य प्रगति पर। -- as on 14-Jun-2024
Physical Peramenters