Work Profile Report [70W527]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन के पत्रांक सं0 294/।।।(3)/2024-01(सी0आर0आई0एफ0)2024, दि0 12.03.2024 एवं पत्रांक 256/।।।(3)/2024-01(सी0आर0आई0एफ0)2022, दि0 09.02.2024, एवं 322/।।।(3)/2024-14(सी0आर0आई0एफ0)2024, दि0 06-03-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1383.21
Resanction Cost :
1383.21
Tentative Cost :
1383.21
Exp. Upto Last Fy :
1,383.21
For CFY 2025-2026
Remaining :
0.00
Demand :
0.00
Allotment :
1,374.95
Exp in CFY :
0.00
Total Up to Date Exp :
1,383.21
Work completed
Sanction on : 1 year 3 weeks ago
12 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
100 %
Tentative Completion date on : 3 weeks 2 days ago
14 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 29-Mar-2025
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: GADIYUNPUL BRIDGE