Work Profile Report [71W1013]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : ई पत्रावली संख्या 45994 दिनांक 12/03/2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
270.20
Resanction Cost :
270.20
Tentative Cost :
270.20
Exp. Upto Last Fy :
0.05
For CFY 2024-2025
Remaining :
270.15
Demand :
270.00
Allotment :
115.00
Exp in CFY :
145.62
Total Up to Date Exp :
145.67
Construction Started
Sanction on : 5 months 4 days ago
12 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
70 %
Tentative Completion date on : 1 month 1 week from now
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 06-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand