Work Profile Report [71W353]

जनपद पौड़़ी गढ़वाल के विधान सभा क्षेत्र लैन्सडौन में कर्तिया जुई मोटर मार्ग का निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0-779/।।।(2)/14-59 (प्रा0आ0)/2013 दि0 26/2/14

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

93.66

Resanction Cost :

93.66

Tentative Cost :

93.66

Exp. Upto Last Fy :

3.09

For CFY 2024-2025

Remaining :

90.57

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

3.09

Construction Started

Sanction on : 10 years 9 months ago

26 Feb 2014

Physical Progress:

At start of FY 2024-2025 :

3 %

Up to Date :

3 %

Tentative Completion date on : 8 months 3 weeks ago

31 Mar 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
6
6
6
-

Remark

view all

वन भूमि हस्तान्तरण हेतु प्रस्ताव आनलाईन किया जा चुका है। -- as on 27-Apr-2024

Rating : 3

Forest Case Pending At : 02: Division

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: