Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 6 | 0 |
71W353 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-779/।।।(2)/14-59 (प्रा0आ0)/2013 दि0 26/2/14
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
93.66
Resanction Cost :
93.66
Tentative Cost :
93.66
Exp. Upto Last Fy : 3.09
For CFY 2024-2025
Remaining : 90.57
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 3.09
Construction Started
Physical Progress:
At start of FY 2024-2025 : 3 %
Up to Date : 3 %
Sanction on :
10 years 4 months ago
26 Feb 2014
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: Long Term Forest Approval
वन भूमि हस्तान्तरण हेतु प्रस्ताव आनलाईन किया जा चुका है। -- as on 27-Apr-2024
Physical Peramenters