Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 4 | 4 | 0 |
72W34 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 3109/111-(2)/06-18 (प्रा0आ0)/06 दि0 23-11-06
TS Amount (lakhs) : 103.5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
103.50
Resanction Cost :
103.50
Tentative Cost :
103.50
Exp. Upto Last Fy : 103.47
For CFY 2024-2025
Remaining : 0.03
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 103.47
Construction Started
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
17 years 7 months ago
23 Nov 2006
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: no issue
किमी0 1 सें 4 तक पहाड कटान एवं स्कपर निर्माण का कार्य पूर्ण। उक्त मोटर मार्ग किमी0 5 से 5.50 के निर्माण हेतु वनभूमि प्रस्ताव गठित किया जा चुका है। इस कार्यालय के पत्रांक 460/14 सी0 दि0 11.05.2023 द्वारा दूरी प्रमाण पत्र के सत्यापन हेतु पत्र लिखा गया है। उपपग्रभागीय वनाधिकारी पौडी के पत्रांक 740/12-1 दि0 27.03.2023 द्वारा आपत्तियों में प्राप्त। आपत्तियों का निराकरण किया जा रहा है। इस कार्यालय के पत्रांक 666/14 सी0 दिनांक 11.05.2023 के द्वारा प्रभागीय वनाधिकारी पौड़ी को दूरी प्रमाण पत्र के सत्यापन हेतु पत्र लिखा गया है। -- as on 30-Dec-2023
Physical Peramenters