राष्ट्रीय राजमार्ग संख्या 309 (बी) के किमी0 10.00 से किमी0 25.00 एवं किमी0 48.00 से किमी0 77.00 तक सुदृढ़ीकरण का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : RO/UK/Annual Plan/2020-21/Ranikhet/02 Date 30-12-2020

TS Amount (lakhs) : 4819.55 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

4819.55

Resanction Cost :

4819.55

Tentative Cost :

4819.55

Exp. Upto Last Fy :

1,013.93

For CFY 2025-2026

Remaining :

3,805.62

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

1,013.93

Construction Started

Sanction on : 4 years 7 months ago

30 Dec 2020

Physical Progress:

At start of FY 2025-2026 :

60 %

Up to Date :

67 %

Tentative Completion date on : 3 months 1 day from now

30 Nov 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
44.1
44.1
44.1
-

Remark

view all

अवशेष कार्य के अन्तर्गत 13.75 किमी0 डी0बी0एम0 के सापेक्ष 12.00 किमी0, 40.30 किमी0 बी0सी0 के सापेक्ष 15.00 किमी0, 26 नं0 बाॅक्स कल्वर्ट के सापेक्ष 9 नं0 बाॅक्स कल्वर्ट पूर्ण एवं नाली 15270 रनिंग मी0 के सापेक्ष 7000 रनिंग मी0 पूर्ण। शेष कार्य प्रगति पर है। -- as on 20-Aug-2025

Rating : 62

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1