Work Profile Report [83W10]

राष्ट्रीय राजमार्ग संख्या 309 (बी) के किमी0 10.00 से किमी0 25.00 एवं किमी0 48.00 से किमी0 77.00 तक सुदृढ़ीकरण का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : RO/UK/Annual Plan/2020-21/Ranikhet/02 Date 30-12-2020

TS Amount (lakhs) : 4819.55 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

4819.55

Resanction Cost :

4819.55

Tentative Cost :

4819.55

Exp. Upto Last Fy :

927.16

For CFY 2024-2025

Remaining :

3,892.39

Demand :

800.00

Allotment :

86.77

Exp in CFY :

86.77

Total Up to Date Exp :

1,013.93

Construction Started

Sanction on : 3 years 11 months ago

30 Dec 2020

Physical Progress:

At start of FY 2024-2025 :

50 %

Up to Date :

60 %

Tentative Completion date on : 1 month 3 weeks ago

29 Oct 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
44.1
44.1
3.800
40.3
9.000
3.700

Remark

view all

अवशेष कार्य के अन्तर्गत 13.75 किमी0 डी0बी0एम0 के सापेक्ष 0.50 किमी0, 40.30 किमी0 बी0सी0 के सापेक्ष 3.70 किमी0, 26 नं0 बाॅक्स कल्वर्ट के सापेक्ष 4.5 नं0 बाॅक्स कल्वर्ट पूर्ण एवं नाली 15270 रनिंग मी0 के सापेक्ष 1200 रनिंग मी0 पूर्ण। शेष कार्य प्रगति पर है। -- as on 03-Dec-2024

Rating : 60

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI:

© PWD Uttarakhand