Work Profile Report [83W10]

राष्ट्रीय राजमार्ग संख्या 309 (बी) के किमी0 10.00 से किमी0 25.00 एवं किमी0 48.00 से किमी0 77.00 तक सुदृढ़ीकरण का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

Administrative Approval Detail : RO/UK/Annual Plan/2020-21/Ranikhet/02 Date 30-12-2020

TS Amount (lakhs) : 4819.55 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

4819.55

Resanction Cost :

4819.55

Tentative Cost :

4819.55

Exp. Upto Last Fy :

927.16

For CFY 2024-2025

Remaining :

3,892.39

Demand :

800.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

927.16

Construction Started

Sanction on : 3 years 7 months ago

30 Dec 2020

Physical Progress:

At start of FY 2024-2025 :

50 %

Up to Date :

55 %

Tentative Completion date on : 2 months 1 week from now

29 Oct 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
44.1
44.1
3.800
40.3
9.000
3.700

Remark

view all

Work in Progress. -- as on 29-Jun-2024

Rating : 62

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI:

© PWD Uttarakhand