Work Profile Report [83W9]

Closed Work राष्ट्रीय राजमार्ग संख्या 309 (ए) के किमी0 131.00 से 134.00 तक बागेश्वर (बाजार क्षेत्र) में ढकी हुई आर0सी0सी नाली का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

Administrative Approval Detail : RO/UK/12014/104/Annual Plan/2019-20 Date 31-03-2020

TS Amount (lakhs) : 387.24 Lacs

Budget Financial Head : Not Available

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

387.24

Resanction Cost :

387.24

Tentative Cost :

387.24

Exp. Upto Last Fy :

266.35

For CFY 2024-2025

Remaining :

120.89

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

266.35

Work completed

Sanction on : 4 years 4 months ago

31 Mar 2020

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

100 %

Tentative Completion date on : 2 years 7 months ago

16 Dec 2021

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Jobs
1
1
1
-

Remark

view all

Work completed. -- as on 03-Apr-2022

Rating : 100

No Forest Case in The Work

Hindrance / Bottleneck :

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: 15m Span RCC bridge (Mandalsera Section)

© PWD Uttarakhand