Work Profile Report [8W11]

जुम्मा - द्रोणागिरी मोटर मार्ग के कागा से गरपक तक मोटर मार्ग एवं 21 मी॰ विस्तार का मोटर सेतु
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 1754/।।।-2/05-64(प्रा॰आ॰)/2005 दि॰ 10.11.05

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : TSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

119.88

Resanction Cost :

119.88

Tentative Cost :

119.88

Exp. Upto Last Fy :

19.39

For CFY 2024-2025

Remaining :

100.49

Demand :

2.50

Allotment :

2.50

Exp in CFY :

0.00

Total Up to Date Exp :

19.39

Survey work done

Sanction on : 19 years 1 month ago

10 Nov 2005

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

16 %

Tentative Completion date on : 3 months 6 days from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
5
5
5
-
Bridge
1 (21m)
1 (21m)
1 (21m)
-

Remark

view all

प्रस्ताव दि॰ 06.10.2022 को आन लाईन कर दिये गये हैं। इस कार्यालय के पंत्राक 2998/ 23 एल0ए0 दिनांक 25.09.2023 द्वारा प्रभागीय वनाधिकारी नन्दा देवी राष्ट्रीय पार्क जोशीमठ को नवनिर्माण 0.918 हे0 वनभूमि आॅनलाईन प्रस्ताव के परिपेक्ष में प्रस्ताव की हार्ड काफी चार प्रतियों में तैयार कर प्रेषित किया गया है। प्रस्तव पर प्रमुख वन संरक्षक एवं नोडन अधिकारी देहरादून द्वारा अपने पंत्राक सं॰ 1043/12-1 दिनांक 30.11.2023 को आपत्तियों में वापस आपत्तियों का निराकरण 20.01.2024 तक कर दिया जायेगा। -- as on 30-Dec-2023

Rating : 17

Forest Case Pending At : 06: Conservator

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: