Work Profile Report [8W11]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : 1754/।।।-2/05-64(प्रा॰आ॰)/2005 दि॰ 10.11.05
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
119.88
Resanction Cost :
25.00
Tentative Cost :
25.00
Exp. Upto Last Fy :
19.39
For CFY 2025-2026
Remaining :
5.61
Demand :
5.00
Allotment :
5.00
Exp in CFY :
0.00
Total Up to Date Exp :
19.39
Survey work done
Sanction on : 20 years 3 weeks ago
10 Nov 2005
Physical Progress:
At start of FY 2025-2026 :
16 %
Up to Date :
16 %
Tentative Completion date on : 3 months 3 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 94.88 has been recorded as expected cost of work reduced from 119.88 to 25 . -- as on 07-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: