Work Profile Report [8W11]

जुम्मा - द्रोणागिरी मोटर मार्ग के कागा से गरपक तक मोटर मार्ग एवं 21 मी॰ विस्तार का मोटर सेतु
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : 1754/।।।-2/05-64(प्रा॰आ॰)/2005 दि॰ 10.11.05

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : TSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

119.88

Resanction Cost :

25.00

Tentative Cost :

25.00

Exp. Upto Last Fy :

19.39

For CFY 2025-2026

Remaining :

5.61

Demand :

5.00

Allotment :

5.00

Exp in CFY :

0.00

Total Up to Date Exp :

19.39

Survey work done

Sanction on : 20 years 3 weeks ago

10 Nov 2005

Physical Progress:

At start of FY 2025-2026 :

16 %

Up to Date :

16 %

Tentative Completion date on : 3 months 3 weeks from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
5
5
5
-
Bridge
1 (21m)
1 (21m)
1 (21m)
-

Remark

view all

Overall Saving 94.88 has been recorded as expected cost of work reduced from 119.88 to 25 . -- as on 07-Dec-2025

Rating : 18

Forest Case Pending At : 07: Nodal

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: