Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 90 | 90 | 90 | 0 |
8W159 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 7075/।।।(2)/13-41 (प्रा0आ0)/2013 दि॰ 20.12.2013
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 97.65 Lacs
Resanction Cost : 97.65 Lacs
Exp. Upto Last Fy : 16.04 Lacs
For CFY 2024-2025
Remaining : 81.61 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 16.04 Lacs
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
10 years 4 months ago
20 Dec 2013
Tentative Completion date:
1 month 1 week ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: Long Term Forest Approval
01.वन भूमि प्रस्ताव दिनांक 27-12-2023 को ऑनलाइन कर दिया गया है | वर्तमान में प्रस्ताव डी0 एफ0 ओ0 स्तर पर है।
02. मार्ग के संरेखण में आने वाले 75 मी॰ स्पान सेतु की डी0पी0आर0 गठित की जा चुकी है। मोटर मार्ग की वास्तविक लंबाई 0.600 किमी0 एवं 75 मी0 मोटर लौह सेतु के निर्माण का विस्तृत आगणन, लागत रु॰ 1115.71 लाख का अधीक्षण अभियन्ता, गोपेश्वर के पत्रांक 2514/442 याता-7/2023 दि॰ 22.05.2023 द्वारा मुख्य अभियन्ता, पौड़ी को प्रेषित। मुख्य अभियंता पौडी का पत्रांक 4229/07(71) याता0 -गापेश्वर -पौडी/2023 दि॰ 30.08.2023 द्वारा उक्त विस्तृत आगणन कतिपय आपत्तियों में खण्ड को प्राप्त, सेतु से सम्बन्धित आपत्तियों का निराकरण हेतु इस कार्यालय के पत्रांक 2940/1 सी0 दि0 18.09.2023 द्वारा मै0 टी0सी0एस0 दे0 दून को पत्र प्रेषित।
-- as on 02-Jan-2024
Physical Peramenters