Work Profile Report [8W430]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : HOD no- 895/07 Yata-PMGSY-Ni-III
TS Amount (lakhs) : 40.43 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
40.43
Resanction Cost :
40.43
Tentative Cost :
40.43
Exp. Upto Last Fy :
33.22
For CFY 2024-2025
Remaining :
7.21
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
33.22
Work completed
Sanction on : 1 year 7 months ago
16 May 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 7 months 2 weeks ago
24 May 2024
Actual Completion Date : 1 year 5 days ago
07 Jan 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 10-Jun-2024
Assets :