Work Profile Report [9W17]

पंगोट दैचोरी मार्ग का नव निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Nabard
  • Tenders

  • Aggrements
  • Project Activities

  • alerts
  • Documents

    Samples

Administrative Approval Detail : 3157/।।।(2)/ 06-71(प्रा0आ0)/ 06 दिं0 18.12.2006

TS Amount (lakhs) : 356 Lacs

Budget Financial Head : NABARD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

356.00

Resanction Cost :

356.00

Tentative Cost :

268.29

Saving

87.71

Exp. Upto Last Fy :

185.99

For CFY 2024-2025

Remaining :

170.01

Demand :

130.00

Allotment :

68.09

Exp in CFY :

68.09

Total Up to Date Exp :

254.08

Work completed

Sanction on : 18 years 1 week ago

18 Dec 2006

Physical Progress:

At start of FY 2024-2025 :

90 %

Up to Date :

100 %

Tentative Completion date on : 3 months 5 days from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
20
18.2
4.750
13.45
2.250
0.000

Remark

view all

मार्ग मे 4.750 किमी0 का कार्य पूर्ण वर्तमान में बचत से 2.250 किमी0 का कार्य प्रगति पर है। -- as on 04-Dec-2024

Rating : 103

Forest Case Pending At : 15: AIP Nodal

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI:

© PWD Uttarakhand