Work Profile Report [9W415]
Tenders
alerts
Documents
Samples
Administrative Approval Detail : 5082/III(2)2023-01(PE)/2023 Lok Niman Anubhag - 02 dt. 09-11-2023
TS Amount (lakhs) : 549.66 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
549.66
Resanction Cost :
549.66
Tentative Cost :
549.66
Exp. Upto Last Fy :
254.70
For CFY 2025-2026
Remaining :
294.96
Demand :
0.00
Allotment :
200.00
Exp in CFY :
0.00
Total Up to Date Exp :
254.70
Construction Started
Sanction on : 1 year 5 months ago
09 Nov 2023
Physical Progress:
At start of FY 2025-2026 :
80 %
Up to Date :
80 %
Tentative Completion date on : 2 months 1 week ago
31 Jan 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 12-Apr-2024
Assets :